We used Poli-Void, a flexible expansion joint material from Stegmeier that is placed prior to pouring the concrete, at the back of each stair tread so we could easily remove the top 1⁄4 inch of foam to make room for the caulking crew to do their job once our work had been completed. The Poli-Void also gave me a good reference point for the placement height of the concrete. Each step was poured and allowed to set, then it was stripped, finished and saw-cut the same day (see photo 6). Using a step groover, we grooved in control joints at 18- to 20-foot intervals to allow for shrinkage upon drying. This was done in case the set time of the concrete was accelerated due to the weather conditions. (It was summertime and the temperature was warm, plus the site was wide open [see photo 7] and winds could have caused the concrete to dry rapidly.) Every crack-control joint was cut in approximately 10 to 12 hours after placement with a 14-inch high-speed cut-off saw fitted with a diamond blade designed for cutting green concrete. Note: We always make a small test slab with each pour to check for timing on the early saw-cuts. If the test slab cuts clean without spalling, there is a good chance the main piece will cut clean as well. Test slabs also are handy to have if you are trying different sealers or using acid stains to see what your outcome will be before executing the work on the main piece. The one dilemma we encountered during construction was when we installed the bottom step and had nothing to mount our form brackets to. We may not have achieved as perfect a radius as with the other steps if we only used pins to hold the formwork. To make our forms fit the work, we simply poured a temporary footing to attach our brackets to and discarded it after use (see photo 8).
|
|
||||||||||
|
|
|||||||||||



